Spread the love
Panorama view into worlds biggest industrial hops extraction plant with supercritical CO2 top with big bags
Spread the love

Project story · CO₂ hop extraction

In September 2020, Europe was at a standstill. Borders were closed, business travel was close to impossible and many construction sites had gone quiet. At the same time, in St. Johann, right in the heart of Bavaria’s Hallertau hop-growing region, a plant started up that had no equal anywhere: the world’s largest CO₂ hops extraction plant. Engineered and built by Natex, based in Ternitz, Austria. And right on schedule.

Here is a look behind the scenes at how that worked out despite the pandemic, and which technical problems had to be solved along the way.

0
high-pressure extractors
0 l
volume per extractor
0 bar
operating pressure
0 t
raw hops per year

The brief: hop extract for breweries around the world

The client was Hopfenveredlung St. Johann GmbH, a joint venture of hop merchant BarthHaas and the hop processing cooperative HVG. According to the operator, around a quarter of the world’s hop harvest is processed at the site. The new Natex CO₂ plant handles approximately 10,000 tons of raw hops per year.

The end product doesn’t look like much: a deep-green extract with the viscosity of honey. It contains the alpha acids, the very compounds that give beer its bitterness. Brewers value the extract because it can be dosed precisely in the brewhouse, speeds up the brewing process and takes up less storage space than pelletized hops.

Two years of groundwork before the first bolt went in

A plant of this size doesn’t come out of a catalogue. Before the final order was placed, the project already had around two years of engineering groundwork behind it. From there, it took almost exactly two more years to commissioning.

At its heart are eight high-pressure extractors of 4,500 litres each, designed for an operating pressure of 550 bar. For comparison: a car tyre runs at around 2.5 bar. The extractors operate at more than 200 times that.

Eight 4,500-litre high-pressure extractors for CO2 hop extraction

In a nutshell

Why so much pressure?

Above 31 °C and about 74 bar, carbon dioxide behaves neither quite like a gas nor quite like a liquid. In this “supercritical” state it penetrates the raw material like a gas while dissolving compounds like a liquid. The higher the pressure, the more it can dissolve. For the fundamentals, see our page on supercritical CO₂ technology.

Hops are a demanding raw material

Depending on the variety, hops contain high levels of essential oils. Great for the aroma of the beer, a real challenge for the equipment. Proven plant components that run smoothly with other raw materials therefore had to be specifically adapted.

The way there was systematic testing: Natex analysed, and at times learned the hard way, how the hops behave under different process conditions and translated the findings into individual engineering solutions. That’s how we work on every project: each plant starts with trials in our own pilot facility, whether for hops, coffee or an entirely new raw material.

Mid-build: the pandemic

The second big challenge had nothing to do with process engineering. The COVID-19 pandemic hit right in the middle of the realization phase. Travel between Austria and Germany was suddenly heavily restricted, and you cannot commission a plant of this size over a video call.

With special permits and a well-coordinated team that kept things moving between Ternitz and St. Johann even under these conditions, the first sections of the plant went into operation on schedule in September 2020.

Installation of the hops extraction plant in St. Johann during construction
A high-pressure extractor being lifted into place by crane on the St. Johann construction site

From the project lead

“A strong team, mutual trust, and a shared determination to see the project through were ultimately the keys to success.

For me, the HD19 project at Hopfenveredlung Sankt Johann was far more than just a technical assignment. It was demanding, varied, and personally challenging, but also an incredibly rewarding and valuable learning experience.

Of course, HD19 had its share of problems, unexpected developments, and situations that presented us with new challenges. The COVID-19 pandemic was a particular challenge, placing additional demands on us and making collaboration and project delivery considerably more difficult. Limited face-to-face contact, difficulties coordinating our work, and constantly changing circumstances required a great deal of flexibility and understanding from everyone involved.

Even beyond the pandemic, things did not always go according to plan, and some tasks proved considerably more demanding than initially expected. This called for difficult decisions, flexibility, and, above all, perseverance.

It was precisely during these times that teamwork, mutual support, and open and honest communication with everyone involved in the project mattered most. Only by working together were we able to overcome the challenges and bring the project to a successful conclusion.

HD19 was a project that demanded a great deal from us, but also taught us a great deal. It was an intense, exciting, and valuable experience. A strong team, mutual trust, and a shared determination to see the project through were ultimately the keys to success.

I am delighted that we successfully completed HD19 together. I am proud of what we achieved and grateful to have been part of this special project.

Peter Luef
Project Manager, Natex Prozesstechnologie GesmbH

The celebration came later: the official opening of the site had to be postponed because of the pandemic and took place in October 2022, attended, according to the operator, by the Minister President of Bavaria.

The project in four stages

  1. Phase 1approx. 2 yearsEngineering groundwork

    Trials with the raw material and plant design, before the final order was placed.

  2. Phase 2almost 2 yearsManufacturing and installation

    From the order to commissioning, from 2020 onwards under pandemic conditions.

  3. MilestoneSeptember 2020Commissioning

    The first sections of the plant go into operation on schedule.

  4. MilestoneOctober 2022Grand opening

    Postponed because of the pandemic, then officially celebrated.

Energy efficiency by design

Sustainability wasn’t an afterthought on this project. It was part of the design brief from day one. Three things make the difference:

CO2 separator of the hops extraction plant for recovering carbon dioxide

In a plant that processes thousands of tons around the clock, details like these add up to a noticeable cost factor over the years.

Built for the next 40 years

The St. Johann plant is designed for decades of operation. A look at Italy shows that this isn’t an empty promise at Natex: the decaffeination plant for Lavazza has been running since 1991 and today processes more coffee than it was originally designed for.

For all technical data and photos of the hops plant, see the full project page on the world’s largest hops extraction plant.

Fact box

The plant at a glance

Operator
Hopfenveredlung St. Johann GmbH (BarthHaas and HVG)
Location
St. Johann, Hallertau, Bavaria (Germany)
Processing capacity
approx. 10,000 t of raw hops per year
Extractors
8 vessels, 4,500 litres each, designed for 550 bar
Project duration
approx. 2 years of groundwork + approx. 2 years to commissioning
Commissioning
September 2020 (first sections), on schedule
Grand opening
October 2022
Product
CO₂ hop extract for breweries, rich in alpha acids
Special feature
CO₂ recovery down to below 1 bar, energy-optimized process design

Frequently asked questions

The plant built by Natex in St. Johann, Bavaria, processes approximately 10,000 tons of raw hops per year. It runs eight high-pressure extractors of 4,500 litres each, designed for 550 bar.

The hops are pelletized and loaded into the extractors. Carbon dioxide at high pressure (supercritical CO₂) dissolves the valuable compounds such as alpha acids and hop oils. The CO₂ is then separated and reused, leaving a pure, solvent-free hop extract.

For the St. Johann plant it took about four years: roughly two years of engineering groundwork, then almost exactly two more years from the final order to commissioning in September 2020.

The extract is concentrated, speeds up the brewing process, takes up less storage space, has a longer shelf life and can be dosed precisely in the brewhouse. That means consistent bitterness from one brew to the next.

Pilot trials instead of guesswork

Your raw material, your plant

Whether hops or any other natural raw material: we run trials in our own pilot facility to determine yield and extract quality, then design the plant to match your volumes. From lab scale to world record.

related news & insights.